Completed milestones are separated from scheduled or reported future events so the record stays clear as CVN-81 takes shape.

January 20, 2020 · Naming announced

The Navy named the future Gerald R. Ford-class carrier USS Doris Miller (CVN-81) during a ceremony at Pearl Harbor.

August 25, 2021 · First cut of steel

Newport News Shipbuilding ceremonially marked the first cut of steel and early manufacturing for Doris Miller.

2022 · Ship sponsors announced

The Navy announced Charlene Austin and Taya Miller as sponsors for the future USS Doris Miller.

2024–2026 · Fabrication and outfitting

HII has continued work on CVN-81 as part of its new-construction carrier program.

FY2026 · Keel laying scheduled

Program material has scheduled CVN-81's keel laying for fiscal year 2026. This remains a future milestone until completed and announced.

2034 · Current planned delivery

The Navy's Fiscal Year 2027 shipbuilding budget moved CVN-81's projected delivery from February 2032 to February 2034 because of shipyard construction-space constraints. Future schedules remain subject to change.

A note about construction dates: CVN-81 is an active shipbuilding program, so planned milestones can move as Navy requirements, shipyard capacity and program decisions change. CVN-81.com distinguishes completed events from scheduled or reported future dates and updates them against U.S. Navy and Huntington Ingalls Industries (HII) / Newport News Shipbuilding sources whenever possible.